The following is the response to a question placed at the Council Meeting in February – for your information:



COMHAIRLE CONTAE ÁTHA CLIATH THEAS
SOUTH DUBLIN COUNTY COUNCIL




MEETING OF SOUTH DUBLIN COUNTY COUNCIL

Monday, February 13, 2012

QUESTION NO. 8

QUESTION: Councillor J. Hannon

To ask the Manager for a comprehensive report outlining how the Boherboy Scheme costs have escalated from €33.5 million to €53 million, with costings included for any additional works carried out and providing the rationale for such works. Can he also outline the sources of funding and the amount in each case, and how South Dublin's portion of this cost is being financed, and at what cost?

REPLY:

The civil works for the above scheme were included in Contract No. 2 and were being executed by Pierse Contracting Limited prior to their liquidation in November 2010. At the time of their liquidation between 5 and 10% of the works under Contract No. 2 remained to be completed and these outstanding works were included in Contract No. 5 – Completion Contract, which is currently being executed by Ward & Burke Construction Limited. The Final Estimate for Contract No. 2, the ‘Pierse Contract’, was €34,840,875.97 including VAT.